Country: Iran
Area/Province: East Azarbayjan
Client: East Azarbayjan Regional Water Authority
Main Contractor: FARAB
Supplier: HYDRONIK SAZEH
Designer: Farab Equipment Manufacturing Co.
Scope: Design, material supply, manufacturing and installation
Project Type: EPC
Start Date: Mar - 2007
Weight (ton): 1300 ton
Equipment: Spillway radial gates, spillway stoplog gates, spillway lifting beam, bottom outlet maintenance gate, bottom outlet maintenance emergency gate and casing, bottom outlet steel lining, irrigation including pipe, Y branch and reducer, several types of gantry and overhead cranes, types of roller and slide gates, hydraulic servomotors, irrigation and power inside steel lining, electrical and control equipment
Capacity: ----
Status: Executed