S.No |
Project Name |
Field of Activity |
Equipment |
Qty / Weight |
Designer |
Status |
1 |
Masjed Soleyman Extension 1000 MW (4 x 250) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine Butterfly Valve Governor Pressure Parts |
4 Units |
Voith Hydro - Austria Litostroj Power (Slovenia) Voith Hydro - Austria |
Executed |
2 |
Karoun VI 1000 MW (4 × 250) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine Butterfly Valve Governor Pressure Parts |
4 Units |
Voith Hydro - Austria Litostroj Power (Slovenia) Voith Hydro - Austria |
Executed |
3 |
Upper Gotvand Extension 1000 MW (4 × 250) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine Butterfly Valve |
4 Units |
Voith Hydro - Austria Litostroj Power (Slovenia) |
Executed |
4 |
Siah Bishe 1000 MW (4 × 250) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine - Pomp Generator - Motor Governor Pressure Parts |
4 Units |
Voith Hydro - Austria Voith Fuji (Japan) Voith Hydro - Austria |
Executed |
5 |
Seymare 480 MW (3 × 160) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine Generator Governor Pressure Parts |
3 Units |
Alstom (Switzerland – France) |
Executed |
6 |
Sang Toudeh (Tajikistan) 220 MW (2 × 110) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Generator Equipmen |
2 Units |
HEC (China) |
Executed |
7 |
Azad 10.2 MW (3 × 3.4) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine |
3 Units |
FARAB Equipment Manufacturing Co. |
Executed |
8 |
Darian 210 MW (3 × 70) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine، Generator Equipmen |
3 Units |
HEC (China) |
Executed |
9 |
Sardasht 150 MW (3 × 50) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Turbine |
3 Units |
HEC (China) |
Executed |
10 |
Shahriar |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Hydromechanical equipment |
1300 ton |
FARAB Equipment Manufacturing Co. (EPC) |
Executed |
11 |
Azad |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Draft tube gates and penstock |
75 ton |
FARAB Equipment Manufacturing Co. (EPC) |
Executed |
12 |
Darian |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Draft tube gates |
90 ton |
FARAB Equipment Manufacturing Co. (EP) |
Executed |
13 |
Haraz |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Diversion roller gate steel lining equipment (Drinking pipeline) |
25 ton 250 ton |
FARAB Equipment Manufacturing Co. (EPC) |
Executed |
14 |
Terem (Kenya) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Radial & stoplog gates |
40 ton |
FARAB Equipment Manufacturing Co. (EP) |
Executed |
15 |
Sardasht |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Draft tube & diversion tunnel gates |
100 ton |
FARAB Equipment Manufacturing Co. (EP) |
Executed |
16 |
Deralok 2 (Iraq Kurdistan) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Trash rack gates Radial gates stoplog gates |
150 ton 350 ton 420 ton |
FARAB Equipment Manufacturing Co. (EPC) |
In Progress |
17 |
Deralok 2 (Iraq - Kurdistan) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Trash rack cleaning machine (TRCM) 1.5 ton |
1 pcs |
EMIS (Italy) |
In Progress |
18 |
Oma Oya (Serilanka) |
Supply of main equipment for infrastructure projects |
Trash rack cleaning machine (TRCM) 3 ton |
1 pcs |
EMIS (Italy) |
In Progress |
19 |
Mehrian II 3 MW (2 × 1.5) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Horizontal Francis Turbine |
2 Units |
FARAB Equipment Manufacturing Co. |
Executed |
20 |
Seymare 480 MW (3 × 160) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Vertical Francis Turbine |
3 Units |
FARAB Equipment Manufacturing Co. |
Executed |
21 |
Upper Gotvand Extension 1000 MW (4 × 250) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Vertical Francis Turbine |
4 Units |
FARAB Equipment Manufacturing Co. |
Executed |
22 |
Ostur 240 MW (4 × 60) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Butterfly Valve |
4 Units |
FARAB Equipment Manufacturing Co. |
Executed |
23 |
Khoda Afarin 210 MW (3 × 70) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Butterfly Valve |
3 Units |
FARAB Equipment Manufacturing Co. |
Executed |
24 |
Azad 10.2 MW (3 × 3.4) |
Supply of main equipment for hydro power plants (Local manufacturing management of hydro power plants main equipment) |
Vertical Francis Turbine |
3 Units |
FARAB Equipment Manufacturing Co. |
Executed |